HNL - Energy Anytime Anywhere
HNL
Hybrid Power System for K-Electric Grid Substations
Client:K-Electric
Industry:Energy & Utilities
Location:Karachi, Sindh
Duration:18 months

Hybrid Power System for K-Electric Grid Substations

Ensuring grid stability with intelligent power backup for Karachi's critical infrastructure

The Challenge

K-Electric, Karachi's sole electricity provider serving 25 million people, faced a critical challenge at their 132kV and 66kV grid substations. During load shedding and grid instabilities, auxiliary systems at these substations would fail, causing cascading outages affecting thousands of industrial and residential customers.

Key Pain Points

  • 115-20 critical substations experiencing auxiliary power failures monthly
  • 2Aging diesel backup systems with 40% failure rate during emergencies
  • 3Average 45-minute delay in manual generator startup during outages
  • 4PKR 35M monthly in industrial customer penalty claims
  • 5High diesel and maintenance costs for 35-year-old generator fleet
  • 6No visibility into substation power status until customer complaints
  • 7Environmental compliance pressure from SEPA regulations

Business Impact: Each substation failure triggered cascading outages affecting 50,000-200,000 customers. Industrial customers were claiming PKR 35M monthly in SLA penalties, and K-Electric's reputation was suffering with a Net Promoter Score of -12.

The Opportunity

Modern hybrid power systems could provide instantaneous backup during grid instabilities while dramatically reducing lifecycle costs. The opportunity extended beyond cost savings to improving K-Electric's service reliability metrics and customer satisfaction.

Project Scope

15 critical 132kV and 66kV substations across Karachi's industrial and high-density residential areas. Each substation required 200-500kW of backup capacity for auxiliary systems including SCADA, protection relays, cooling systems, and lighting.

The Solution

HNL engineered a comprehensive hybrid backup solution combining rooftop solar, industrial-grade BESS, and modernized diesel generators with seamless transfer switching. The system provides instantaneous switchover (<20ms) ensuring zero disruption to critical substation equipment.

1

Critical Load Analysis

Detailed assessment of each substation's auxiliary loads, categorizing into Tier-1 (SCADA, protection - no interruption allowed), Tier-2 (cooling, essential lighting - 100ms tolerance), and Tier-3 (general loads - 1s tolerance).

2

Hybrid Architecture Design

Three-tier power architecture: Grid primary + BESS for instant backup + Solar for daytime charging + Diesel for extended outages. UPS integration for Tier-1 loads with 10ms transfer.

3

Industrial BESS Selection

Selected high-power density lithium batteries rated for 10C discharge to handle substation inrush currents. Total 2.4 MWh storage capacity across 15 sites.

4

Smart Energy Management

Custom EMS integrating with K-Electric's existing SCADA to predict outages and pre-charge batteries. AI-based algorithms optimize solar utilization and battery cycling.

5

Diesel Modernization

Replaced aging generators with modern Cummins units featuring auto-start, load-sharing, and remote monitoring. Diesel now serves as fourth-tier backup only.

6

Centralized Monitoring

All 15 substations connected to K-Electric's central control room with real-time visibility into power status, battery health, solar generation, and predictive alerts.

Technical Specifications

battery Capacity160 kWh average per site (2.4 MWh total)
battery TypeIndustrial LiFePO4, 10C discharge rated
solar Capacity500 kW total across 15 sites
transfer Time<20ms to battery, <10ms for UPS-protected loads
diesel Backup400 kVA per site, 8-hour runtime
monitoringIntegrated with K-Electric SCADA
design Life15 years battery, 25 years system

Execution Timeline

1

Phase 1: Engineering & Procurement

Months 1-6
  • Detailed site surveys and load studies
  • Protection coordination studies
  • System architecture finalization
  • Equipment procurement (8-week lead time for batteries)
  • Factory acceptance testing
  • Civil and structural assessments
2

Phase 2: Pilot Installation

Months 7-9
  • Installation at 3 pilot substations
  • System integration with existing switchgear
  • SCADA integration and testing
  • Commissioning and performance validation
  • Operator training at pilot sites
3

Phase 3: Full Deployment

Months 10-16
  • Phased rollout to remaining 12 substations
  • Night-time installations to minimize disruption
  • Integration testing at each site
  • Progressive system handover
  • Documentation and as-built drawings
4

Phase 4: Optimization & Support

Months 17-18
  • System performance optimization
  • AI model training on actual outage patterns
  • Comprehensive operator training program
  • Warranty activation and SLA commencement
  • Handover to K-Electric O&M team

Project Gallery

Electrical substation

132kV grid substation in Karachi

Industrial battery system

Industrial-grade BESS installation

Solar panels on rooftop

Rooftop solar array at substation

Control room monitoring

Centralized monitoring integration

The Outcome

Annual Savings
120M

PKR reduction in operational and penalty costs

Substations
15

Critical grid substations upgraded

Transfer Time
<20ms

Instant backup activation

Penalty Reduction
95%

SLA penalty claims eliminated

Uptime
99.99%

Auxiliary system availability

Diesel Reduction
75%

Generator runtime reduced

Business Impact

revenue: PKR 120M annual savings through reduced diesel, maintenance, and eliminated SLA penalties
market Share: K-Electric NPS improved from -12 to +18 in covered areas within 6 months
customer Satisfaction: Industrial customer retention rate improved from 78% to 94%

"The hybrid power solution delivered by HNL has transformed our substation reliability. We went from firefighting mode to proactive operations. The instantaneous switchover means our customers don't even know when the grid hiccups anymore. This project has become a model for our future infrastructure investments."

A
Ali Hassan
Chief Operating Officer, K-Electric

Key Learnings

  • Critical infrastructure requires <20ms transfer times - standard UPS is insufficient
  • Integration with existing SCADA maximizes operational value
  • Night-time installation scheduling essential for utility projects
  • Predictive AI can pre-position systems before outages occur
  • Industrial battery ratings (C-rate) matter more than capacity alone
  • Stakeholder alignment across utility operations teams is critical

Looking for Similar Results?

Our team is ready to discuss your infrastructure, energy, or IT project and deliver measurable outcomes for your organization.

Ready to Power Your Next Project?

Partner with Pakistan's leading infrastructure and energy solutions provider. Let's build something extraordinary together.